WHAT IS THE PROCESS &
HOW LONG WILL IT TAKE?

The Downtown Specific Plan process began with project kickoff in October 2024 and is now in its final phase of review and approval. Over the course of the process, the City conducted extensive outreach, including community workshops, stakeholder interviews, online questionnaires, a multi-day open house, and public hearings.

Following adoption by the Planning Commission and City Council, the City will transition into implementation of the Plan. Implementation will occur over time and will depend on available funding, staff capacity, and partnerships with public and private stakeholders.

Specific Plan Timeline

Specific Plan Timeline Graphic

Public Review Complete — Public Hearing Draft

Now Available

DTSP Cover page image.png

Downtown Specific Plan Public Review Draft

DTSP Appendix Cover page image.png

Downtown Specific Plan Appendices

The public review period has concluded, and the Final Public Hearing Draft Downtown Specific Plan and appendices are now available here.

 

​An Open House and Steering Committee meeting were separately held on February 17, 2026, to review the Downtown Specific Plan draft. Applicable comments have been incorporated into the Final Public Hearing Draft. The Plan is tentatively scheduled for Planning Commission on May 13, 2026, and City Council on June 3, 2026.

An additional Steering Committee meeting will be held on April 13, 2026, to discuss the committee’s ongoing role in plan implementation.

Photo of Steering Committee Tour

Steering Committee
Meetings

The Downtown Specific Plan process was initiated in October 2024 with a Downtown tour conducted alongside a Steering Committee composed of representatives from a range of local stakeholder groups. The Committee has met multiple times throughout the planning process to provide input and guidance. An additional meeting is scheduled for April 13, 2026, to discuss the Committee’s ongoing role in plan implementation.

Public Meeting Photo

Community Workshop
January 9, 2025

A community workshop was held at the WOW Classroom Building. The team shared our observations and existing conditions analysis findings and gathered initial feedback. Click on the Workshop Presentation link below to see what was discussed at the community workshop.

Public Meeting Photo

Community Open House,
February 4 & 5, 2025

A multi-day Open House was held at 22 South Main Street and the event included presentations in both English and Spanish. The activities allowed for multiple opportunities for interactive public participation to review the findings, discuss thoughts and ideas, and generate initial design concepts for Downtown Lodi.

Community Open House
April 17, 2025

The City hosted an Open House at 22 South Main Street which allowed for additional public review of the project team's findings and analysis and provided an opportunity to obtain input from the community. The event included presentations in both English and Spanish. 

04.17.25 English DTSP Flyer.jpg
04.17.25 Spanish DTSP Flyer.jpg
IMG_8322_edited.jpg

 

Two Study Sessions were held to discuss the Downtown Specific Plan’s purpose and status, summarize community outreach to date, highlight opportunities and preliminary concepts, and clarify the next steps in the process. Both Study Sessions took place at the Council Chambers in the Carnegie Forum at 305 West Pine Street.

Planning Commission

Study Session

April 23, 2025

Link to Agenda

Link to Facebook Video Feed

Link to Power Point (PDF)

City Council

Study Session

May 7, 2025

Link to Video

Link to Power Point (PDF)

Downtown Specific Plan Update

The City of Lodi, in coordination with its consultant team, has completed an extensive outreach process to gather community input on the Downtown Specific Plan. This process included public workshops, surveys, Steering Committee meetings, and presentations to the Planning Commission and City Council. Feedback received throughout this process has been incorporated into the Final Public Hearing Draft of the Plan.

The Plan is now in its final phase of review and approval, with public hearings scheduled before the Planning Commission and City Council. Following adoption, the City will transition into implementation of the Plan.

This PDF was previously presented as a project update to the Steering Committee on August 11, 2025, City Council on September 3, 2025, and the Lodi Improvement Committee on September 9, 2025.